Answer in brief
Before you send anything, find out who receives it, through which channel, and what you must keep. Below you find a starting point for your situation, an opening letter you can copy, questions for a developer, a filing log with one row per country and, at the end, what the three official pages say, each sentence with its link and the date we read it. We compare no countries by score.
Your next step
You have a letter to write, or one to answer
Name the country, the substation and the body you wrote to. We reply by hand.
What happens to your enquiry →Which row is yours? Start from your situation
| Your situation | Begin with | Do not do yet |
|---|---|---|
| A developer asks to option your land and says the grid is arranged | Your country's row below, then a written request for proof that an application was filed. | Sign an option that runs longer than the time the receiving body needs to answer. |
| You are a developer or fund and hold a site but no application | The signature route and the channel in your country's row, so that the application is filed by someone entitled to file it. | Count the site as secured on the strength of a map or a public list alone. |
| You compare a site in one country with a site in another | Both country rows side by side, noting where one body publishes a rule and the other publishes nothing we could find. | Treat a gap in the table as proof that the step does not exist. |
Order of work when you hold the plot, not the connection
- Start with the country row, not with the developer's pitch: a developer who cannot name the receiving body for your plot has not filed yet.
- Ask the developer which of the three steps in the filing log further down it has completed, and ask to see the document, not a summary.
- Write the dates of every reply on the same sheet as the substation name, so that a later gap in the chain shows at once.
- Hand a developer only what you hold in writing, and mark the rest as unknown.
Your opening letter, line by line
A short letter that a clerk can answer in one reply gets answered sooner than a long one that raises five questions. Write it in the language the body works in, or attach a translation you can stand behind, and put the following in this order.
- Who you are and in what capacity you write: owner of the plot, holder of an option, developer, or fund.
- The plot or the connection point, named so that a stranger can find it: parcel identifier, municipality and the nearest substation.
- What you want to connect, in plain terms: the kind of load, the capacity you hope for and the year you would need it.
- The one question you need answered, followed by the reply you would find useful, so that the clerk can see what a complete answer looks like.
- The date by which you need the reply for your own planning, and the person who may answer on your behalf.
- A closing line that names every attachment, so that nothing is lost between inboxes.
Five slips that cost owners months
- Signing an option before you have seen one document that proves an application exists in your plot's name or the developer's.
- Letting a developer file in your name without a copy of the filing reaching you the same day.
- Keeping replies in a phone or a chat thread instead of a file that a lawyer could open.
- Reading a public list as a promise: a name on a list tells you where an application stands, and nothing about what happens next.
- Waiting for a perfect letter. A plain question sent this week beats a polished one sent after the quarter has closed.
Questions to put on the table before you sign an option
- Who filed the application, on which date, and may I see the filing receipt?
- Which connection point does it name, and is that the same substation your design assumes?
- What has the receiving body written back so far, and is any of it a refusal or a request for more documents?
- Does the option you are asked to sign end if the body says no, and who pays for the work done until then?
- Who may speak to the receiving body for you, and will you be copied on every message?
Build your filing log before you write
Whichever market you choose, the same three habits protect you: name the body that receives the request, keep each reply with its date, and put a question to that body in writing before you rely on anything for money. The log below turns that into one row per country.
| Country | Settle before you write | Keep in your file | Ask the body in your opening letter |
|---|---|---|---|
| Bulgaria | Who signs for you. ESO ties portal access to a registration made in person or through a notarised power of attorney (ESO, connection page, read ). | The registration form as signed, the date of the portal confirmation, and the power of attorney if someone signs for you. | Whether your connection point appears in ESO's register of those wishing to connect under the temporary access scheme (ESO, connection page, read ). |
| Poland | Which route you file through. PSE names its ESOP platform for applications from (PSE, list of entities applying for connection, read ). | The filing receipt, the date of any request to complete the application, and the rules text you read when you filed. | Whether your application is shown as awaiting verification or as confirmed complete in PSE's published lists (PSE, list of entities applying for connection, read ). |
| Germany | Who the connecting network operator is for your plot, and whether a flexible connection agreement would suit your load (Bundesnetzagentur, Netzanschluss, read ). | The grid company's written reply, the connection point it names, and its words on any construction cost contribution. | Whether the grid company would offer a flexible agreement, and what the Baukostenzuschuss covers in your case (Bundesnetzagentur, Baukostenzuschüsse, read ). |
What each official page says, row by row
| Country | Topic | What the official page says | Read on |
|---|---|---|---|
| Bulgaria | Who you apply to, and how | ESO gives access to its Information Portal after a registration that the applicant makes in person, or an authorised person makes with a notarised power of attorney, on a standard form signed with the applicant's qualified electronic signature (ESO, connection page). | |
| Bulgaria | What is published about steps and rules | ESO names a register of those who wish to connect to the grid under a temporary access scheme (ESO, connection page). | |
| Bulgaria | What is published about steps and rules | ESO links a map under the label “free capacity for connection”; we have not read the map and quote nothing from it (ESO, free capacity for connection). | |
| Bulgaria | What is published about steps and rules | Collecting: the list of documents an application needs under the ordinance. We read ESO's connection page on and found no such list there (ESO, connection page). | |
| Bulgaria | What the regulator says | ESO quotes Ordinance No. 6 of on connecting sites to the electricity networks, issued by the chair of the Energy and Water Regulation Commission (EWRC) and amended, the latest amendment it cites in force from (ESO, connection page). | |
| Poland | Who you apply to, and how | PSE says that from an application for connection conditions can be filed through its electronic connection platform, ESOP (PSE, list of entities applying for connection). | |
| Poland | What is published about steps and rules | PSE publishes the entities applying for connection to the transmission grid, the applications for connection conditions (those awaiting verification and those confirmed complete) and the refusals it has issued, as Art. 7 ust. 8l of the Energy Law requires (PSE, list of entities applying for connection). | |
| Poland | What is published about steps and rules | PSE also publishes a uniform set of rules describing the procedures, regulations, deadlines and criteria it applies when it considers connection applications (Art. 7 ust. 8p) (PSE, list of entities applying for connection). | |
| Poland | What is published about steps and rules | Aggregated information on connections to the transmission and distribution grids is part of that publication, and PSE says the information under Art. 7 ust. 8m is updated at least monthly (PSE, list of entities applying for connection). | |
| Poland | What the regulator says | Collecting: a description of the connection steps from URE, the Polish regulator. We read its home page and consumer guide on and found none (URE, home page). | |
| Germany | Who you apply to, and how | The Bundesnetzagentur says the physical and technical link to the grid is governed by the connection relationship between the party to be connected and the network operator (Bundesnetzagentur, Netzanschluss). | |
| Germany | Who you apply to, and how | Collecting: a list of application steps and documents. We read the Bundesnetzagentur page on and found none (Bundesnetzagentur, Netzanschluss). | |
| Germany | What is published about steps and rules | For storage and consumption facilities the Bundesnetzagentur explains flexible connection agreements (FCA), which § 17 para. 2b of the Energy Industry Act (EnWG) regulates and which serve to allow connections with restrictions where connection capacity is scarce (Bundesnetzagentur, Netzanschluss). | |
| Germany | What is published about steps and rules | It adds that network operators have the option but no explicit legal duty to offer an FCA, and that the details are agreed by contract between applicant and connecting network operator (Bundesnetzagentur, Netzanschluss). | |
| Germany | What is published about steps and rules | The Bundesnetzagentur describes the construction cost contribution (Baukostenzuschuss) as a one-off payment for expanding the general grid, made to the network operator when the connection is built (Bundesnetzagentur, Baukostenzuschüsse). | |
| Germany | What the regulator says | It states that under the EnWG network operators must connect final consumers, other grids, and generation and storage facilities on reasonable, non-discriminatory and transparent terms (Bundesnetzagentur, Netzanschluss). | |
| Germany | What the regulator says | It also says the connection and its use are a precondition for network access, which enables the grid company's transport service (Bundesnetzagentur, Netzanschluss). |
We publish no price, waiting time or ranking of countries, because we hold no source for one.
Where the figures for each market live
- Bulgaria: the request totals ESO reports and what they mean for a plot are on GridBourse.
- Poland: the fees, advances and validity PSE states for a large load are on GridBourse, and the substations without free connection places are on a page of their own.
Questions and answers
Why do you not rank the three countries?
Because the official pages describe different things in different words, and a score would hide that. We quote each page and leave the comparison to you.
Is this legal advice?
Ask the grid operator, the regulator and a lawyer before anything that decides money. We quote official pages and give no legal advice.
What if my country or my operator is missing?
Tell us the plot and the substation you have in mind. When we find an official page for it, we add a row with its source and read date.
Sources and as-of dates
- ESO, connection page eso.bg, retrieved .
- ESO, free capacity for connection webapps.eso.bg, retrieved .
- PSE, list of entities applying for connection pse.pl, retrieved .
- URE, home page ure.gov.pl, retrieved .
- Bundesnetzagentur, Netzanschluss bundesnetzagentur.de, retrieved .
- Bundesnetzagentur, Baukostenzuschüsse bundesnetzagentur.de, retrieved .